Project Bid Opportunities

Project Bid Opportunities

Construction Contract Projects for the Valley Center Municipal Water District are advertised and awarded in accordance with provisions of the Public Contract Code. Projects are advertised in Newspapers of general circulation in the area of the project and also in various Construction Trade Journals and Newsletters. Contracts are awarded to the lowest responsible bidder as required by the Code. The following Construction Contracts are currently out for bid:

 


Jesmond Dene Reservoir Demolition 1

[Project No. 01-06-78-51302]

 

Bid Date: Tuesday, February 25, 2020 at 3:00 PM. 

Engineers Estimate:  $125,000

Addendums: There is 1 addendum for this project.

The project generally consists of the removal and disposal of a 55-foot diameter by 25-foot tall (base to roof) 0.42 million gallon above ground bolted steel potable water reservoir, above ground and below ground piping,  concrete reservoir ringwall, oiled sand and gravel below reservoir and AC Pavement/Dike surrounding the reservoir. The contractor shall remove and dispose of the interior/exterior ladders and associated brackets, tabs and all other components, rafters, central vent, overflow pipe and other miscellaneous material as shown on the plans. Existing above grade 12” altitude valve, 4” and 12” gate valves shall be removed and returned to the District upon removal. A 12” blind flange (150 lb) shall be installed at the existing 12” flanged tee. Drainage infrastructure, surface improvements and soil import to grade the site at 1% minimum are required as shown on the Contract Drawing.  Contractor shall take precautionary measures in protecting and existing overhead electrical line traversing the site. Contractor shall be responsible for cleaning all construction debris after all demolition work is complete.

 

All work shall be completed in THIRTY-FIVE (35) calendar days.


  Full Project Description


WEST BEAR RIDGE AND PARADISE MOUNTAIN NO. 1 RESERVOIR PAINTING AND RECOATING PROJECT

[Project No. 01-06-78-51302]

 

Bid Date: Tuesday, February 25, 2020 at 2:00 P.M. 

Engineers Estimate:             West Bear Ridge: $925,000

                                                Paradise Mountain No. 1 Reservoir: $280,000

Addendums: There is 1 addendum for this project.

Information on obtaining Addendums, Plans, Specifications, and Contract Documents:

The Project generally consists of the cleaning, remedial repair, interior coating, and exterior painting of West Bear Ridge, a 165-foot diameter by 27-foot tall (base to roof) 4.3 million gallon above ground welded steel potable water reservoir and Paradise Mountain No. 1, a 74-foot diameter by 32-foot tall (base to roof) 1.0 million gallon above ground welded steel potable water reservoir and above ground piping including, but not limited to the following work components.  The contractor shall remove and dispose of the interior ladder and associated brackets, tabs, and all other components prior to coating.  Contractor shall remove existing center vents and screens on each reservoir prior to interior work and replace vent when complete.  Screens to be replaced by Contractor after completion of all painting and coating.  Contractor shall replace all existing earthquake straps/rods and associated nuts/bolts prior to interior coating on each reservoir.  Contactor shall remove and replace all existing rafter tail nuts/bolts prior to coating.  Contractor shall remove existing weld splatter prior to coating or painting on each reservoir.  Existing conduits, radios, antennas, and other miscellaneous electrical and radio components on each reservoir will remain protected in place during Contractor’s work.  All electrical and radio components to be painted or protected as directed by District. The number of rafters to be replaced will be determined by the District upon inspection after interior coating removal. Contractor to provide an alternate bid price for rafter replacement. 

  Full Project Description